ANALISIS PENJADWALAN ULANG DENGAN MENGGUNAKAN METODE LSM (LINIER SCHEDULING METHOD/ LINE OF BALANCE) (RESCHEDULING ANALYSIS WITH LSM/LOB METHOD)
Abstract
In conducting project development phases, planning and scheduling is the
most decisive phase of successful or whether a project. the project scheduling method is planned
for the implementation of the project to be effective and efficient. In project implementation, there
is often less utilization of project work time effectively because the methods used are less suitable
for the type of the project itself. So as to wasted unnecessary time.
A scheduling method with the appropriate type of planned projects, very influential on the
effectiveness of utilization of project development time itself. In a housing construction project,
usually using the type or types of the same building. This is the underlying to using the LSM
(Linier Scheduling Method / Line of Balance) to perform rescheduling. The determination of
working groups of typical and continuous work item is one of the advantages of this
method are basically give priority to quantity of the type of work that does not inhibit the type of
work the next (the successor and predecessor).
And of the results of the analysis that has been carried out , then obtained the time needed
to carrying out a project development of a housing complex green valley 171 90 units which was
during the day .While in the case of time schedule existing the project plan to it takes 360 days to
menyelesaiakan 90 this unit .With compare the effectiveness of that time did so in which runs for
the day differed 189 , the plans to cut down a method of LSM more effective and efficient in the
project development of a housing complex development green valley