| dc.description.abstract | Productivity is a fundamental factor that influences the performance of competitiveness in the
construction industry. Increasing the level of productivity relates to the time needed to complete
the work and will directly affect the amount of costs needed. Particularly from the reduction in
costs consumed by construction workers. The costs allocated to these workers contribute to the
auction / tender process and during the implementation of the project, therefore information
about labor productivity is very important to be examined in detail. One way to get field
productivity value is by using method productivity delay model. In this study there are 5 labor
that observed. Observation take 3 session .first session held before 12 pm, second session held
after 12 pm. And third session take randomly beetwen that 2 session. Based on the research that
has been done, the results of the analysis are as follows. Field labor Productivity is 2,64 m2/hour
and ideal labor productivity is 3,659 m2/hour. Comparation of field productivity and unit price
analysis from PermenPUPR-28-2016 is 23,936 times. Biggest delay factor affect productivity is
material factor. | en_US |
| dc.publisher | Universitas Islam Indonesia | en_US |
| dc.subject | Productivity, Labor, Auto Claved Aerated Concrete, MPDM | en_US |
| dc.title | Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Bata Ringan Dengan Menggunakan Method Productivity Delay Model (MPDM) | en_US |
| dc.type | Article | en_US |