| dc.description.abstract | The implementation of the Pekanbaru city wastewater pipeline construction project is likely to
raise many risks that must be considered by stakeholders because the impact of the risks is
detrimental and can affect the overall project completion with regard to time, cost, and quality.
This research describes the implementation of risk management in the Pekanbaru city wastewater
pipeline construction project based on the risk management concept of ISO 31000:2018. The
questionnaire survey is the first phase of the data collection for the research project in order to
obtain risk level and risk respond. Then, the survey results are validated based on the
respondent’s opinion from the interview. Based on interview, it was also known the risk control
undertaken by stakeholders to resolve the risks. In the whole process of risk management, the
implementation of the ISO 31000:2018 was only achieved 87,5%, this happens because the risk
analysis is only carried out by the contractor while others do not. Therefore, only contractors
implement completely of the risk management process according to ISO 31000:2018. | en_US |