Analisis progres realisasi proyek terhadap biaya pada proyek jembatan kereta api rangka baja Surakarta
Date
2023-07-18Author
Ghiffary, Muhammad F
Mukti, Fathoni A
Firdaus, Ad Zulfa G
Sulistyantoro, Tri N
Metadata
Show full item recordAbstract
The steel frame railway bridge construction project in Surakarta is an
ongoing national strategic project. Analysis of the progress of project
realization on the cost of implementing important infrastructure projects
is carried out on this project. Construction management involves
managing human resources, material resources and financial resources
to manage a construction project from start to finish. Analysis of the
progress of project realization against costs is carried out using the unit
price analysis method. The unit price of work involves the price of labor
wages, the price of materials, and the price of tools used in the project.
In this analysis, the reference is based on the 2022 Surakarta City Work
Unit Price Analysis (AHSP). From the stages of analysis carried out,
including searching for references, identifying problems, taking data
processing and analysis, as well as presenting research results to
competent construction parties, and discussions and conclusions
obtained the results of work costs of 98,80 billion rupiah with the addition
of PPN 10,87 billion rupiah, so that the final cost of 109,66 billion rupiah
was obtained. The results of the analysis show the unit price of wages,
materials and work tools used in the Surakarta steel frame railway bridge
project. This analysis is carried out so that this project can be completed
on time and in accordance with the available budget allocation. This
analysis is used as a consideration about the financial performance of the
project and helps ensure that the project is proceeding according to the
established budget plan.