Pra-Rancangan Pabrik Styrene Dari Ethylbenzene Dengan Kapasitas 100.000 Ton/Tahun
Abstract
Preliminary plant design of Styrene from Ethylbenzene is targeting to domestic demand and an export quota. This chemical plant is designed with the capacity
100.000 tons/year. The process will be operated at the temperature 450 C, at the pressure of about 1 atm using catalyst of Shell 105 with total conversion of 40 %. This plant will be built in Cilegon, the province of West Java on the area of
53.930 m2• This plant will be operated for 24 hours/day and 330 days a year with the total employess of 145. Raw material needed are Ethylbenzene of about 21803.6372 kg/hour and total steam of about 19795.4361 kg/hour.
This plant requires water as much as 29931.9904 kg/hour. The electricity is supplied by PLN with capacity 183.9824 KW.
The economics analysis shows that Break Event Point (BEP) of this chemical plant is 42.23 %, Shut Down Point (SDP) 28.56 %, Return of Invesment after taxes 26.2045% and Pay Out Time (POT) after taxes for about 2.7621 years.