ANALISIS PEMILIHAN KOMBINASI ALAT BERAT PADA PEKERJAAN GALIAN DAN PEMUATAN TANAH PADA PEMBANGUNAN KANTOR TAHAP II KANTOR PELAYANAN PAJAK DAERAH SLEMAN (HEAVY EQUIPMENT COMBINATION CHOICE ANALYSIS ON EXCAVATION AND LOAD SOIL OF CONSTRUCTION OFFICE OF KPPD SLEMAN OFFICE CONSTRUCTION STEP II)
Abstract
The construction of the phase ii kppd sleman will heap does the work of mining and land
.The job will be done by some heavy instrument commonly used in mining and work the excavator
heap , wheel loaders , and dump truck .The purpose of this research is to know the right
combination of heavy equipment levels as can be seen from the cost and time work .
To get combination heavy equipments which optimally conducted by with calculate several
an alternative combination.Of the results of the analysis calculation or four alternative
combination instrument which includes combination excavator, wheel loader, and dump
truck.From the condition real he it took 327 hours and cost rp.295.565.700-. While for first
alternative the amount of time that are necessary during the 154 hours with fund of
rp.160.156.600,00-.In the second one is the amount of time that are necessary during the 157
hours at a cost of 158.197.200,00- and on alternative third it takes time for seven hours to the
amount of charge 172.682.500,00-.
So could be seen from several the results of an alternative that is applied side by side
comparisons with the condition of real in the ground in a comparison in order to get a
combination of a tool that optimal .So that these chareges in the future the first alternative as a
combination of the optimum in terms of their own the time and money spent consisting 1 a unit of
excavator , 2 a unit of wheel loader and 18 dump to based on the recommendation of on the job
diggers should manage roads and abdomen is like a heap the ground at office development the
stage of 2 kppd sleman