| dc.description.abstract | Productivity of mechanical equipment is a critical factor in overburden stripping operations
because it directly affects coal exposure and production continuity. At Pit 3 Banko, PT Bukit
Asam Tbk, overburden removal is performed using one Komatsu PC3000 shovel and three
Belaz 75135 haul trucks. Operational observations indicate that production performance has
not reached optimal levels, suggesting an imbalance within the shovel-haul truck system. This
research evaluates equipment productivity using cycle time analysis, work efficiency
calculation, match factor assessment, and Discrete-Event Simulation (DES) with FlexSim.
Field observations show an average shovel cycle time of 3.44 minutes and haul truck cycle time
of 20.9 minutes. Work efficiency is 51.39% for the shovel and 47.92% for haul trucks, reflecting
considerable non-productive time. The existing configuration produces a match factor of 0.49
(49.4%), indicating significant shovel idle time due to insufficient truck availability. Simulation
results reveal that increasing the fleet to six haul trucks improves the match factor to 0.987
(98.7%), creating a near-balanced system and minimizing idle time. Adding seven trucks results
in overcapacity (MF = 1.15) and truck queuing. Therefore, six haul trucks represent the optimal
configuration under current operating conditions. The integration of analytical and simulation
approaches provides a realistic basis for improving overburden stripping productivity without
additional major equipment investment. | en_US |
| dc.language.iso | en | en_US |
| dc.publisher | Universitas Islam Indonesia | en_US |
| dc.subject | Overburden Stripping | en_US |
| dc.subject | Shovel and Haul Truck System | en_US |
| dc.subject | Productivity Analysis | en_US |
| dc.subject | Match Factor | en_US |
| dc.subject | Discrete Event Simulation | en_US |
| dc.subject | Mining Operations Efficiency | en_US |
| dc.title | Analysis of the Productivity of Shovel and Haul Truck In Overburden Stripping Operations at PIT 3 Banko, PT Bukit Asam, Tanjung Enim, South Sumatera | en_US |
| dc.type | Thesis | en_US |
| dc.Identifier.NIM | 22522162 | |