Analisis Estimasi Biaya dan Waktu Pelaksanaan Pekerjaan AC-WC berdasarkan Observasi Lapangan
Date
2022-07-20Author
Widayat, Wisanggeni Paramusesa
Musyafa, Albani
Sulistyantoro, Tri Nugroho
Metadata
Show full item recordAbstract
Manpower is one of the factors that have an important role in the success of a
construction project. The workforce itself is closely related to the cost and time of a
construction project which can be controlled in the budget plan (BOQ) and the Time
Schedule. This BOQ estimate really needs to be used to calculate the income and expenses of
the contractor and related parties for the smooth implementation of the project. The estimation
calculation from the interview will be changed again using the coefficients that the authors
have calculated with the data obtained through direct surveys during the AC-WC work by the
authors. The calculation of the coefficient of the workers and foreman is calculated from the
weight and effective working time of the workers and foremen of the AC-WC work per day
from the beginning of the implementation of the AC-WC work until the end of the AC-WC
work. The direct field survey in this project also found data on the time required for this AC
WC work. The results showed that AC-WC work with a width of 7-7.5 m, a length of 3,150 km,
a thickness of 4 cm, a slope of 2%, a volume of 2.153,01 tons, requires an implementation cost
of Rp. IDR 2.323.097.790,00. If excluding overhead and profit, is Rp 2.020.084.860,70. AC
WC work with these specifications also requires execution time of 6 days with a total time of
37 hours 35 minutes 24 seconds.