Risk assessment berdasarkan konsep 4 pilar keselamatan konstruksi pada pekerjaan blasting
Date
2023-07-18Author
Firmansyah, Mochamad
Wibowo, Agung
Nugraheni, Fitri
Metadata
Show full item recordAbstract
The construction sector is a high-risk business sector. One of the risks in
the construction world can be sourced from construction safety aspects
following PERMEN PUPR No. 10 of 2021 (labor, tools, materials, and
environment). Risk management in managing the company is something
that needs to be considered in the steps to minimize risk. The subject of
this research is construction safety risk, and the object of this research is
blasting work at the Bener Dam. Risk identification is carried out by
deepening the WBS, then conducting a risk probability and impact
assessment on respondents. Risk assessment uses probability and impact
matrix. The results showed that there were 47 risks, consisting of 10 risks
in the moderate category, 34 risks in high risk, and 2 risks in very high
risk.